Set a daily, weekly, or monthly full scan of a project’s default branch.

[Open OpenHack](https://app.openhack.com) and select the organization and project you want to work in.

Scheduled full scans automatically analyze the connected repository's default branch. Configure a schedule separately for each project.

## Before you start [#before-you-start]

- Sign in as an organization owner to change the schedule. Scheduling is configured per project, but changing it is restricted to organization owners because a schedule consumes organization scan usage.
- [Connect a GitHub repository](https://openhack.com/docs/platform/github) to the project.
- Use a plan with full scans enabled. The scheduling screen shows whether your project is eligible.

## Create a schedule [#create-a-schedule]

1. Open the project's **Settings → Scheduled scans**.
2. Find **Scheduled full scans** and turn on the switch.
3. Select **Daily**, **Weekly**, or **Monthly** under **Frequency**.
4. For weekly scans, select **Day of week**. For monthly scans, select **Day of month**.
5. Set **Time**, checking the time zone displayed beside the field.
6. Choose **Save schedule**.
7. Confirm the saved **Next scan** date and time.

Choose the intended time zone in the form. The form displays the saved schedule's time zone when you return; do not assume the displayed time is UTC. For a monthly day that does not exist in a shorter month, the schedule uses that month's last day.

![Project settings showing a weekly Monday scan schedule and the next scheduled run.](https://openhack.com/docs/images/platform/acme/scheduling.png)

_Check the saved time zone and next scan date. Actual product screen with fictional ACME demo data._

## Review scheduled runs [#review-scheduled-runs]

Open **Scans** to inspect the run and its findings. The schedule shows the next planned scan; it does not guarantee that analysis has completed at that time. Check scan history for completion or failure details.

## Change or pause a schedule [#change-or-pause-a-schedule]

Edit the frequency, day, or time and choose **Save schedule**. To pause future scheduled runs, turn off the switch and save. Pausing the schedule is separate from cancelling a scan already in progress.

## If a scan does not start [#if-a-scan-does-not-start]

Check that the repository is still connected, the organization still has full-scan access, and the schedule is enabled and saved. Review any status message beneath the schedule and inspect scan history before starting another run.